To install click the Add extension button. That's it.

The source code for the WIKI 2 extension is being checked by specialists of the Mozilla Foundation, Google, and Apple. You could also do it yourself at any point in time.

4,5
Kelly Slayton
Congratulations on this excellent venture… what a great idea!
Alexander Grigorievskiy
I use WIKI 2 every day and almost forgot how the original Wikipedia looks like.
Live Statistics
English Articles
Improved in 24 Hours
Added in 24 Hours
Languages
Recent
Show all languages
What we do. Every page goes through several hundred of perfecting techniques; in live mode. Quite the same Wikipedia. Just better.
.
Leo
Newton
Brights
Milds

Tanda thermal power plant

From Wikipedia, the free encyclopedia

Tanda Thermal Power Station
Map
CountryIndia
LocationAmbedkarnagar, Uttar Pradesh
Coordinates26°33′00″N 82°39′00″E / 26.55000°N 82.65000°E / 26.55000; 82.65000
StatusOperational
Owner(s)NTPC
Thermal power station
Primary fuelCoal
Power generation
Units operational4×110 MW 2x660 MW
Nameplate capacity1760 MW
External links
Websitewww.ntpc.co.in

Tanda Thermal Power Station is located in Ambedkar Nagar district in the Indian state of Uttar Pradesh. The power plant is one of the coal based power plants of NTPC. The coal for the power plant is sourced from North Karnpura Coal Fields. Source of water for the power plant is from Tanda Pump Canal on Saryu River.

In the year 2000, Uttar Pradesh State Electricity Board (U.P.S.E.B.) transferred Tanda Thermal Power Plant to NTPC Limited against payment overdue. After acquisition of this plant, because of the better maintenance by NTPC Limited, this power plant has crossed its Plant Load Factor (P.L.F.) to more than 100%.

YouTube Encyclopedic

  • 1/3
    Views:
    118 393
    34 120 408
    392 896
  • NTPC Tanda Ambedkar Nagar ki sair टांडा की सैर अंबेडकरनगर
  • Thermal Power Plant | Boiler | Economizer | Turbine | Khan GS Research Centre
  • Top 10 Thermal Power Plant of INDIA (in Hindi)

Transcription

Installed capacity

Stage-I and present installed capacity are listed below:

Unit Number Installed Capacity (MW) Date of Commissioning Status
1 110 Running
2 110 Running
3 110 Running
4 110 Running

For Stage-II, NTPC Limited has installed two new units of 660 MWs each.

Unit Number Commissioned Capacity (MW) Date of Commissioning Status
5 660 Oct-2019 Running
6 660 27 March 2021 Running

Stage-I  : 4x110 MWs = 440 MWs

Stage-II : 660 MW + 660MW = 1320 MW

Total Power Generation : 1760 MWs

References

This page was last edited on 24 February 2022, at 14:50
Basis of this page is in Wikipedia. Text is available under the CC BY-SA 3.0 Unported License. Non-text media are available under their specified licenses. Wikipedia® is a registered trademark of the Wikimedia Foundation, Inc. WIKI 2 is an independent company and has no affiliation with Wikimedia Foundation.