To install click the Add extension button. That's it.

The source code for the WIKI 2 extension is being checked by specialists of the Mozilla Foundation, Google, and Apple. You could also do it yourself at any point in time.

4,5
Kelly Slayton
Congratulations on this excellent venture… what a great idea!
Alexander Grigorievskiy
I use WIKI 2 every day and almost forgot how the original Wikipedia looks like.
Live Statistics
English Articles
Improved in 24 Hours
Added in 24 Hours
Languages
Recent
Show all languages
What we do. Every page goes through several hundred of perfecting techniques; in live mode. Quite the same Wikipedia. Just better.
.
Leo
Newton
Brights
Milds

Trung Sơn Dam

From Wikipedia, the free encyclopedia

Trung Sơn Dam
Location of Trung Sơn Dam in Vietnam
CountryVietnam
LocationTrung Sơn commune, Quan Hóa District, Thanh Hóa Province
Coordinates20°36′32″N 104°50′13″E / 20.60889°N 104.83694°E / 20.60889; 104.83694
StatusOperational
Construction began2012
Opening date2016
Construction costUS$410.68 million
Owner(s)Vietnam Electricity
Dam and spillways
ImpoundsMa River
Height84.5 m (277 ft)
Length513 m (1,683 ft)
Width (crest)8 m (26 ft)
Reservoir
Total capacity348.5×10^6 m3 (282,500 acre⋅ft)
Catchment area14,660 km2 (5,660 sq mi)
Surface area13.13 km2 (5.07 sq mi)
Maximum water depth160 m (520 ft)
Power Station
Commission dateSeptember 2017
Turbines4 X 65 MW Francis turbines
Installed capacity260 MW
Annual generation1,018 GWh

The Trung Sơn Dam (Dự Án Nhà máy Thủy điện Trung Sơn) is a hydroelectric power station on the Ma River in northwestern Vietnam. Located in the Trung Sơn commune, Quan Hóa District, Thanh Hóa Province, it is approximately 95 kilometres (59 mi) southwest of Hòa Bình city, and 195 kilometres (121 mi) northwest of Thanh Hóa city. The dam created a reservoir which covers a large area of the Mường Lát and Quan Hóa Districts in the Thanh Hoa province as well as part of the Mộc Châu District in Sơn La Province. It is approximately 9.5 kilometres (5.9 mi) from the Vietnam–Laos border. The 260 MW associated power plant became fully operational in September 2017.[1]

YouTube Encyclopedic

  • 1/1
    Views:
    69 930
  • Giải đáp thắc mắc về THỦ DÂM - thủ dâm có lợi ích? tác hại gì?

Transcription

The Project

The Trung Sơn hydropower project is owned by Trung Sơn Hydropower Company Limited (TSHPCo), the entity established by Vietnam Electricity (EVN) in Decision No. 106/QD-ENV dated March 17, 2011. TSHPCo is responsible for the management, construction and operation of the Trung Sơn hydropower project.

The project provides both power generation and flood control. The powerhouse is designed to contain four generating units with a total capacity of 260 MW and an annual output of 1,018.61 GWh,[citation needed], a significant addition to the national grid. The flood control storage of 112 million cubic metres (4.0×10^9 cu ft) will help prevent floods downstream.

The project cost a total of VND 7,775,146 million (equivalent to US $410.68 million).[2] This includes US $330 million from a World Bank loan, which was signed by the Socialist Republic of Vietnam and the World Bank on June 28, 2011. Additionally, the project was given slightly over US $80 million from the counterpart fund of (EVN).

The project has created social, environmental and community relation programs to mitigate anticipated and unanticipated issues with populations either directly or indirectly impacted, the Resettlement, Livelihoods and Ethnic Minorities Development Program (RLDP). These populations consist of approximately 10,600 people (2,327 households), of which 7,012 (1,516 households) will be directly impacted in the main project area, resulting in a total of 533 households having to be resettled. The RLDP includes a Resettlement Plan (RP), a Community Livelihoods Improvement Plan (CLIP) and an Ethnic Minorities Development Plan (EMDP).

In addition, management has prepared a Supplementary Environmental and Social Impact Assessment (SESIA) with Environmental Management Plan (EMP) for the project. This plan includes principles, approaches, procedures and methods to be used to control and minimize environmental impacts of all project-related construction and operation activities. Compared with fossil-fuel based energy plants of the same size, the dam produces far less greenhouse gas emissions (GHGs). TSHPCo maintains a website at www.trungsonhp.vn where public information is routinely updated.

Main parameters

  • Catchment basin area: 14,660 square kilometres (5,660 sq mi)
  • Reservoir volume: 348.5 million cubic metres (12.31×10^9 cu ft)
  • Reservoir area when at full capacity: 13.13 square kilometres (5.07 sq mi)
  • Full capacity water level: 160 metres (520 ft)
  • Minimum operating water level: 150 metres (490 ft)
  • Maximum flood control storage: 150 million cubic metres (5.3×10^9 cu ft)
  • Regular flood control storage: 112 million cubic metres (4.0×10^9 cu ft)
  • Installed electrical capacity : 260 MW
  • Annual electrical output: 1,018.61 GWh
  • Dam crest length: 513 metres (1,683 ft)
  • Dam width at the top: 8 metres (26 ft)
  • Dam height: 84.5 metres (277 ft)
  • A power plant containing four 65 MW Francis turbines (total installed capacity of 260 MW), each designed for a maximum water head of 72.02 metres (236.3 ft)
  • A 65-kilometer, 220-kV transmission line connecting to the national grid
  • A 20.4-km access road

Components

The project is composed of four components:

  • Dam and Ancillary Construction: (i) Dam and ancillary works; (ii) Access road and bridges; (ii) Temporary transmission line to supply power for construction; and (iv) Project management
  • Permanent power transmission line: 220 kV double-circuit line to connect to the national grid in the Tan Lac district
  • Social and environment impact mitigation concerns: (i) Resettlement; (ii) Livelihoods and ethnic minorities development; (iii) Public health support; and (iv) Environmental management
  • Capacity development and scale-up: Support to bring hydropower projects up to international standards

Allocation of World Bank US$ 330 million loan

Category Amount of the Loan allocated (US$) Percentage of Expenditure to be financed (including tax)
(1) Eligible expenditures under Component 1 and component 3 of the project 302,225,000 100%
(2) Eligible expenditures under component 2 of the project 23,950,000 100%
(3) Eligible expenditures under component 4 of the project 3,000,000 100%
(4) Front-end fee 825,000 Pursuant to Section 2.03 of the Agreement in accordance with Section 2.07 (b) of the General Conditions
Total 330,000,000

Key milestones

  • Commencement of main civil works: November 2012
  • River diversion: Quarter 4, 2013
  • Impoundment: October 2016
  • Operation of Unit No. 1: Quarter 4, 2016
  • Operation of Unit No. 4: Quarter 2, 2017

References

  1. ^ "Commercial operations begin at Vietnam's 260-MW Trung Son hydropower plant". Hydro Review. 7 September 2017.
  2. ^ At the exchange rate of VND 18,932/ USD as published by the State Bank of Vietnam on December 31, 2010

External links

This page was last edited on 26 September 2023, at 21:46
Basis of this page is in Wikipedia. Text is available under the CC BY-SA 3.0 Unported License. Non-text media are available under their specified licenses. Wikipedia® is a registered trademark of the Wikimedia Foundation, Inc. WIKI 2 is an independent company and has no affiliation with Wikimedia Foundation.