To install click the Add extension button. That's it.

The source code for the WIKI 2 extension is being checked by specialists of the Mozilla Foundation, Google, and Apple. You could also do it yourself at any point in time.

4,5
Kelly Slayton
Congratulations on this excellent venture… what a great idea!
Alexander Grigorievskiy
I use WIKI 2 every day and almost forgot how the original Wikipedia looks like.
What we do. Every page goes through several hundred of perfecting techniques; in live mode. Quite the same Wikipedia. Just better.
.
Leo
Newton
Brights
Milds

Milestone (project management)

From Wikipedia, the free encyclopedia

A milestone, when placed in project management software, is done as a zero-time task and appears with a special notation (black diamond in this case).

Milestones are tools used in project management to mark specific points along a project timeline. These points may signal anchors such as a project start and end date, or a need for external review or input and budget checks. Some contracts for products include a "milestone fee" that may be paid out when certain points are achieved.

In many instances, milestones do not impact project duration. Instead, they focus on major progress points that must be reached to achieve success.[1]

YouTube Encyclopedic

  • 1/3
    Views:
    1 812
    11 790
    34 778
  • Project Management in Under 5: What is Milestone Planning?
  • Scheduling with Milestones in Project Management — Episode 16
  • MS Project 2010: Creating and Using MileStones in MS Project

Transcription

Using milestones in scheduling

Milestones can add significant value to project scheduling. When combined with a scheduling methodology such as program evaluation and review technique or the critical path method, milestones allow project managers to much more accurately determine whether or not the project is on schedule. By constraining the dates associated with milestones, the critical path can be determined for major schedule intervals in addition to the entire project. Slack/float can also be calculated on each schedule interval. This segmentation of the project schedule into intervals allows earlier indication of schedule problems and a better view into the activities for which completion is critical.

Milestones are like dashboard reviews of a project. A number of activities, which were planned at the beginning of the project with their individual timelines, are reviewed for their status. This process also gives an opportunity to check the health of the project.

Milestones are frequently used to monitor the progress, but limitations to their effectiveness exist. They usually show progress only on the critical path, and ignore noncritical activities. Resources are commonly moved from noncritical activities to critical activities to ensure that milestones are met. This gives the impression that the project is on schedule, when actually some activities are being ignored.

See also

References

  1. ^ Verzuh, Eric (2008). The Fast Forward MBA in Project Management (3rd ed.). Hoboken, NJ: John Wiley & Sons, Inc. p. 149. ISBN 9780470247891.

External links


This page was last edited on 30 January 2024, at 12:27
Basis of this page is in Wikipedia. Text is available under the CC BY-SA 3.0 Unported License. Non-text media are available under their specified licenses. Wikipedia® is a registered trademark of the Wikimedia Foundation, Inc. WIKI 2 is an independent company and has no affiliation with Wikimedia Foundation.