To install click the Add extension button. That's it.

The source code for the WIKI 2 extension is being checked by specialists of the Mozilla Foundation, Google, and Apple. You could also do it yourself at any point in time.

4,5
Kelly Slayton
Congratulations on this excellent venture… what a great idea!
Alexander Grigorievskiy
I use WIKI 2 every day and almost forgot how the original Wikipedia looks like.
Live Statistics
English Articles
Improved in 24 Hours
Added in 24 Hours
Languages
Recent
Show all languages
What we do. Every page goes through several hundred of perfecting techniques; in live mode. Quite the same Wikipedia. Just better.
.
Leo
Newton
Brights
Milds

Incremental launch

From Wikipedia, the free encyclopedia

Incremental launch bridge construction
Incrementally-launched bridge construction Itz Valley Bridge near Coburg

Incremental launch is a method in civil engineering of building a complete bridge deck from one abutment of the bridge only, manufacturing the superstructure of the bridge by sections to the other side. In current applications, the method is highly mechanised and uses pre-stressed concrete.[1]: 1 

YouTube Encyclopedic

  • 1/3
    Views:
    3 641 230
    2 580
    32 921
  • Bridge construction - Incremental Launching - 3D Animation
  • [CE08] Bridge Incremental Launching Method || CONSTRUCTION METHOD
  • Incremental launching method - ULMA Construction [en]

Transcription

History

The first bridge to have been incrementally launched appears to have been the Waldshut–Koblenz Rhine Bridge, a wrought iron lattice truss railway bridge, completed in 1859. The second incrementally launched bridge was the Rhine Bridge, a railway bridge that spanned the Upper Rhine between Kehl, Germany and Strasbourg, France, completed in 1861 and subsequently destroyed and rebuilt on several occasions.

The first incrementally launched concrete bridge was the 96-metre (315 ft) span box girder bridge over the Caroní River, completed in 1964. The second incrementally launched concrete bridge was over the Inn River, Kufstein in Austria, completed in 1965. The structural engineers for both bridges were Professor Dr Fritz Leonhardt and his partner, Willi Baur.[1]: 1 

The usual method of building concrete bridges is the segmental method, one span at a time.[2]

Method

The bridges are mostly of the box girder design and work with straight or constant curve shapes, with a constant radius. 15-to-30-metre (49 to 98 ft) box girder sections of the bridge deck are fabricated at one end of the bridge in factory conditions. Each section is manufactured in around one week.[citation needed]

The first section of the launch, the launching nose, is not made of concrete, but is a stiffened steel plate girder and is around 60% of the length of a bridge span, and reduces the cantilever moment.[3] The sections of bridge deck slide over sliding bearings, which are concrete blocks covered with stainless steel and reinforced elastomeric pads.

Notable examples

The Millau Viaduct

References

  1. ^ a b "The incremental launching method in prestressed concrete bridge construction" (PDF). Berne, Switzerland: VSL International Limited. April 1977. Retrieved 20 April 2020.
  2. ^ Liu, Xian Peng; Qin, Zong Ping; Leung, L. W.; Yue, Lingling (2007). "Construction of the Precast Segmental Approach Structures for Sutong Bridge" (PDF). ICE Conference 2007. Beijing, China: YWL. Retrieved 20 April 2020.
  3. ^ "The Charming History of the Incremental Launching Method". BridgeTech. The Bridge Engineering eManuals Project. 2020. Retrieved 20 April 2020.

External links

This page was last edited on 28 March 2024, at 03:45
Basis of this page is in Wikipedia. Text is available under the CC BY-SA 3.0 Unported License. Non-text media are available under their specified licenses. Wikipedia® is a registered trademark of the Wikimedia Foundation, Inc. WIKI 2 is an independent company and has no affiliation with Wikimedia Foundation.