To install click the Add extension button. That's it.

The source code for the WIKI 2 extension is being checked by specialists of the Mozilla Foundation, Google, and Apple. You could also do it yourself at any point in time.

4,5
Kelly Slayton
Congratulations on this excellent venture… what a great idea!
Alexander Grigorievskiy
I use WIKI 2 every day and almost forgot how the original Wikipedia looks like.
Live Statistics
English Articles
Improved in 24 Hours
Added in 24 Hours
What we do. Every page goes through several hundred of perfecting techniques; in live mode. Quite the same Wikipedia. Just better.
.
Leo
Newton
Brights
Milds

Hartlepool nuclear power station

From Wikipedia, the free encyclopedia

Hartlepool Nuclear Power Station
Hartlepool nuclear power station
Viewed from the north in July 2022
Map
CountryEngland, United Kingdom
LocationHartlepool, County Durham
Coordinates54°38′6″N 1°10′51″W / 54.63500°N 1.18083°W / 54.63500; -1.18083
StatusOperational
Construction began
  • Unit 1: October 1, 1968 (1968-10-01)
  • Unit 2: October 1, 1968 (1968-10-01)
Commission date
  • Unit 1: August 1, 1983 (1983-08-01)
  • Unit 2: October 31, 1984 (1984-10-31)
Decommission dateExpected to begin March 2026
Owner(s)Central Electricity Generating Board
(1983–1990)
Nuclear Electric
(1990–1996)
British Energy
(1996–2009)
EDF Energy
(2009–present)
Operator(s)EDF Energy
Nuclear power station
Reactor typeGCR - AGR
Reactor supplierNational Nuclear Corporation
Cooling sourceCarbon Dioxide
Thermal capacity2 x 1500 MWth
Power generation
Units operational
Make and modelGeneral Electric Company
Nameplate capacity1,185 MWe[1][2]
Capacity factor
  • Lifetime: (Up to 2021)
  • Unit 1: 68.4%[1]
  • Unit 2: 70.0%[2]
Annual net output5,710.75 GWh (20,558.7 TJ) (2021)[1][2]
External links
WebsiteHartlepool nuclear power station and visitor centre | EDF
CommonsRelated media on Commons

Hartlepool nuclear power station is a nuclear power station situated on the northern bank of the mouth of the River Tees, 2.5 mi (4 kilometres) south of Hartlepool in County Durham, North East England. The station has a net electrical output of 1,185 megawatts, which is 2% of Great Britain's peak electricity demand of 60 GW.[3] Electricity is produced through the use of two advanced gas-cooled reactors (AGR). Hartlepool was only the third nuclear power station in the United Kingdom to use AGR technology. It was also the first nuclear power station to be built close to a major urban area.

Originally planned in 1967, with construction starting in 1969, the station started generating electricity in 1983, and was completed in 1985, initially being operated by the Central Electricity Generating Board. With privatisation of the UK's electric supply industry in 1990, the station has been owned by Nuclear Electric and British Energy, but is now owned and operated by EDF Energy. On 18 October 2010 the British government announced that Hartlepool was one of the eight sites it considered suitable for future nuclear power stations.[4]

The power station will cease power generation in March 2026, prior to defueling and decommissioning.

YouTube Encyclopedic

  • 1/5
    Views:
    638
    413
    2 780 678
    3 434 871
    3 591 036
  • Meet Lee, who has worked at Hartlepool power station for more than 15 years | EDF #WeKnowNuclear
  • Meet Kate, who works in the efficiency office at Hartlepool power station | EDF #WeKnowNuclear
  • Inside The Billion-Euro Nuclear Reactor That Was Never Switched On
  • What If You Fell Into a Spent Nuclear Fuel Pool?
  • Nuclear Reactor - Understanding how it works | Physics Elearnin

Transcription

History

After building the first operational advanced gas-cooled reactor (AGR) nuclear power station at Dungeness, the Central Electricity Generating Board (CEGB) proposed their third AGR station in 1967 to be situated on the edge of the Durham coalfield, near the seaside resort of Seaton Carew. The proposal came at a time when the CEGB's move toward fuels alternative to coal threatened the coal industry's existence. Despite this, and a short ministerial delay, the plans for the Seaton Carew station (which became known as Hartlepool nuclear power station) went ahead. Because the construction of the station was given the go ahead, the National Coal Board were not able to get the CEGB behind the plans for a prototype fluidised bed combustion (FBC) coal station at Grimethorpe in Yorkshire. Because of this, the UK did not build FBC technology.[5]

Sited 1.65 mi (2.66 km) from Seaton Carew, and in the middle of the industrial complex of Teesside, the station was to be built closer to any major urban area than any nuclear power station site had been. To make this acceptable, the station's reactors were to be housed in prestressed concrete pressure vessels.[5]

The station under construction in June 1972

The construction of the power station which was undertaken by Nuclear Design & Construction ('NDC'), a consortium backed by English Electric, Babcock International Group and Taylor Woodrow Construction,[6] began in 1969.

The construction was delayed in 1970, when the Nuclear Installations Inspectorate declared that they were unhappy with part of the station's boiler design, setting the CEGB back £25 million.[5] The station's reactors were supplied by the National Nuclear Corporation, and the station's generating sets by the General Electric Company.[7] Some fourteen years into construction, the first of the station's two units were commissioned in 1983, the other in 1985.[5] The station first generated electricity commercially on 1 August 1983.[8]

Nuclear fuel for Hartlepool power station is delivered and removed via a loading/unloading facility on a 1½ mile branch from the Durham Coast Line.[9]

Visitor centre

In the 1980s, there was an interactive visitor centre on site. There was also an activity centre for school visits which hosted a number of special events. Tours of the power station itself also took place. The centre was closed after privatisation in the 1990s, but a new visitor centre was opened by current operators EDF Energy in 2013.[10]

This centre also hosts 'Crucial Crew' events for school pupils in the local areas.[11] These experiences teach children about health and safety.

2013 turbine fire

At 19:18 on 20 April 2013 a small fire broke out in the turbine hall of unit 2 at the power station while Reactor 2 was being brought back into service. The fire was caused by an oil leak, and ignited lagging surrounding part of the turbine. Reactor 2 was shut down and cooled, mitigating any threat of nuclear contamination. Emergency services attended the fire from stations across the Cleveland area and the fire was extinguished at 19:53. During the incident, fire cover in the Cleveland area was provided by units from Darlington and County Durham.[12]

Specification

The station is of the advanced gas-cooled reactor (AGR) type. It provides electricity for over 3% of the UK using two 1,575 MWth advanced gas-cooled reactors to power two generators (590 MWe + 595 MWe), giving a maximum generating capacity of 1,320 MW.[3][1][2] The station's designed net electrical output is 1,185 MW.[1][2] This is enough electricity to power 1.5 million homes.[8] There are four 17.5 MW auxiliary gas turbines on the site, these had first been commissioned in October 1973.[13]

Future of the station

The power station was originally expected to shut down in 2009, but was given permission by the Nuclear Installations Inspectorate (NII) for an extension of five years in 2007, meaning that it could continue to generate until 2014. In 2010, the lifetime was further extended by another five years, so that generation can continue until 2019.[3][8] The company then began work to extend station lifetime to 2024 and beyond,[14][15] and an announcement was made in November 2013 that the plant would have a further extension to its operating life of 5 years taking the expected decommissioning date to 2024.[16] The 2024 closure was reaffirmed in 2022.[17] An announcement was made in March 2023 that the plant would have an additional extension to its life of 2 years. Taking the expected decommissioning date to March 2026.[18]

Closing the station would reduce the available reactive power in the local grid by 200 MVAr.[19]

New station

In July 2008, the plant's then-operator British Energy, suggested that the site would be a good location for a replacement nuclear power station.[20] Then a year later in July 2009, the UK government named Hartlepool on a list of eleven sites in England and Wales, where new nuclear power stations could be built.[3] On 9 November 2009, the government announced that ten of these sites, including Hartlepool, had been given the go-ahead for the construction of new reactors.[21] If built, the station would use reactors capable of generating 1,800 MW each.[3] It would cost between £5 billion and £6 billion to construct, would employ up to 3,000 construction workers for the possible eight-year construction period, as well as providing 600 full-time jobs once completed. The new station has an anticipated operating life of 60 years.[15]

The plans are opposed by environmental groups such as Friends of the Earth and Stop New Nuclear.[22]

See also

References

  1. ^ a b c d e f "HARTLEPOOL A-1". Power Reactor Information System. IAEA. 29 August 2022. Retrieved 30 August 2022.
  2. ^ a b c d e f "HARTLEPOOL A-2". Power Reactor Information System. IAEA. 29 August 2022. Retrieved 30 August 2022.
  3. ^ a b c d e "Hartlepool Nuclear Power Station". BBC News. 13 July 2009. Retrieved 22 August 2010.
  4. ^ "Nuclear power: Eight sites identified for future plants". BBC News. BBC. 18 October 2010. Retrieved 18 October 2010.
  5. ^ a b c d Patterson, Walter C (1985). "Going Critical: An Unofficial History of British Nuclear Power" (PDF). Friends of the Earth. Paladin Books. pp. 19–22. Retrieved 18 August 2010.
  6. ^ "The UK Magnox and AGR Power Station Projects" (PDF). Archived from the original (PDF) on 27 April 2020. Retrieved 19 September 2010.
  7. ^ "Nuclear Power Plants in the UK – England". Power Plants Around the World. 8 March 2009. Archived from the original on 19 July 2009. Retrieved 22 August 2010.
  8. ^ a b c "Hartlepool". British Energy. Archived from the original (PHP) on 19 July 2011. Retrieved 22 August 2010.
  9. ^ Brailsford, Martyn (2016). Railway Track Diagrams Book 2: Eastern. Frome: Trackmaps. pp. 45A. ISBN 9780954986681.
  10. ^ "New visitor centre opened as Hartlepool Nuclear Power Station gains permission to extend its life by another five years".
  11. ^ Turner, Ed. "Annual child safety initiative enters 23rd year". www.hartlepool.gov.uk. Retrieved 5 January 2022.
  12. ^ "BBC News – Hartlepool Power Station fire: Probe after oil leak in turbine tackle". BBC Online. 21 April 2013. Retrieved 21 April 2013.
  13. ^ Handbook of Electricity Supply Statistics 1989. London: The Electricity Council. 1990. p. 8. ISBN 085188122X.
  14. ^ Payne, Andrew. "Building the Power Station". This is Hartlepool. Retrieved 8 August 2008.
  15. ^ a b "Consent for longer operation". World Nuclear News. World Nuclear News. 17 December 2010. Archived from the original on 1 April 2012. Retrieved 20 January 2011.
  16. ^ "Hartlepool power station to stay open until 2024". BBC News. BBC. 5 November 2013. Retrieved 19 February 2014.
  17. ^ "Heysham 2 and Torness end dates brought forward by EDF". World Nuclear News. 11 January 2022. Retrieved 26 March 2022.
  18. ^ "Extended life for two UK nuclear power stations". BBC News. 9 March 2023. Retrieved 9 March 2023.
  19. ^ "Pennines Pathfinder updates | National Grid ESO". www.nationalgrideso.com. 7 February 2022.
  20. ^ Winnett, Robert (13 July 2008). "Eight new nuclear power stations planned for England". Telegraph.co.uk. London. Archived from the original on 6 August 2008. Retrieved 8 August 2008.
  21. ^ "Go-ahead for 10 nuclear stations". BBC News. 9 November 2009. Retrieved 4 May 2010.
  22. ^ "BBC News – New UK nuclear plant sites named". 23 June 2011. Retrieved 21 April 2013.

External links

This page was last edited on 20 February 2024, at 19:16
Basis of this page is in Wikipedia. Text is available under the CC BY-SA 3.0 Unported License. Non-text media are available under their specified licenses. Wikipedia® is a registered trademark of the Wikimedia Foundation, Inc. WIKI 2 is an independent company and has no affiliation with Wikimedia Foundation.