To install click the Add extension button. That's it.

The source code for the WIKI 2 extension is being checked by specialists of the Mozilla Foundation, Google, and Apple. You could also do it yourself at any point in time.

4,5
Kelly Slayton
Congratulations on this excellent venture… what a great idea!
Alexander Grigorievskiy
I use WIKI 2 every day and almost forgot how the original Wikipedia looks like.
Live Statistics
English Articles
Improved in 24 Hours
Added in 24 Hours
Languages
Recent
Show all languages
What we do. Every page goes through several hundred of perfecting techniques; in live mode. Quite the same Wikipedia. Just better.
.
Leo
Newton
Brights
Milds

DB Engineering & Consulting

From Wikipedia, the free encyclopedia

DB Engineering & Consulting
Headquarters
Berlin
,
Germany
Number of employees
6200 (2024)
Websitehttps://db-engineering-consulting.com/en/

DB Engineering & Consulting (DB E&C) is an international engineering and consulting company of Deutsche Bahn that specialises in consulting, planning, and implementation services for infrastructure and mobility projects in Germany and worldwide. DB Engineering & Consulting was created in Germany at the beginning of April 2016 as a result of the merger of two DB subsidiaries, DB International and DB ProjektBau.

History

DB Engineering & Consulting (DB E&C) originated from the establishment of Deutsche Eisenbahn-Consulting in 1966.[1] Originally an independent entity, it became fully owned by Deutsche Bahn in 2002.[2]

In 2003, Deutsche Eisenbahn-Consulting became a 100% subsidiary of DB ProjektBau, a newly formed DB company.

By 2007–2008, Deutsche Eisenbahn-Consulting underwent rebranding as DB International. Operating independently within the DB Group, DB International focused on client business in domestic and international markets, while DB ProjektBau concentrated on domestic projects.

In 2016, DB ProjektBau and DB International merged, forming DB Engineering & Consulting.[3][4][5] In the same year, DB E&C expanded its services by acquiring DB Umweltservice (formerly Bahn-Umwelt-Zentrum), expanding its range of services to include environmental analyses.[6][7]

In 2017, DB E&C established the DB Rail Academy product division and started offering international vocational training and professional development for the transport sector.[8][9]

The following year, DB Engineering & Consulting acquired infraView.[10] DB Engineering & Consulting, DB International Operations, and infraView were merged under the DB E.C.O. Group in 2019.

In 2020–2021, DB Engineering & Consulting acquired engineering and software developer ESE GmbH and acquired shares in inno2grid.

Activities

The company is focused on 6 main areas: design, construction supervision, consulting for mobility and logistics services and digitalisation, project management, validation and assessment, and environmental and geoservices.[11][12][13][14]

The company employs around 6200 people in 2024 and is headquartered at the EUREF Campus in Berlin-Schöneberg. DB E&C has many locations in Germany and offices worldwide.[15][16]

Since 2019, the company has been part of DB E.C.O. Group, in which the companies DB International Operations, infraView, ESE Engineering und Software-Entwicklung, inno2grid and DB E.C.O. North America, as well as local companies, subsidiaries and investments worldwide, have been bundled alongside DB E&C.[17][18]

The company is certified in accordance with DIN EN ISO 9001 and DIN EN ISO 45001 by DEKRA. It is a member of UIC, UITP, VDEI, VDV, DVWG and other national and international specialist and trade associations;  also registered with international financing institutions.[19]

Projects

Near/Middle East

Etihad Rail DB Operations, UAE

In 2006, DB was commissioned to carry out a feasibility study for a rail network in the UAE. DB (and since 2016, DB E&C) supported the rail infrastructure development in a joint venture, ERDB, and advised on-site. The key focus was implementing and monitoring test operations on the built and equipped lines and their transfer to regular operations.[20][21]  

Haramain high-speed rail project, KSA

The Haramain high-speed rail project is designed to connect the cities of Mecca, Jeddah, and Medina with a high-speed passenger transportation line. DB E&C is responsible for planning, construction supervision, and vehicle procurement in this project. The project comprises a new electrified passenger railway line of 449 km in length with a commercial operating speed of 300 km/h. It establishes five stations, one in each of the major cities of Makkah, Madinah, Jeddah and King Abdullah Economic City (KAEC), in addition to King Abdullah Airport (KAIA). In the city of Makkah and Madinah the stations are based on the principles of the terminus while in Jeddah and KAEC the stations are based on the principles of through stations.

DB has also agreed to continue advising the railroad companies in the first year after the start of operations. DB E&C is also involved in a number of metro construction projects.[22][23][24][25]

Israel Railways Electrification Program

DB Engineering & Consulting is actively involved in Israel Railways' Electrification Program, providing technical and management consultancy, engineering, and training tasks. The program aims to electrify 420 km of double track lines, including various infrastructure upgrades such as transformer substations, SCADA operation centers, communication systems, and signaling system alterations. DB E&C's role includes providing technical expertise for tender preparation and evaluation, reviewing technical documentation, developing rules and procedures for electrified operation, and assisting in recruitment and training of new employees. Additionally, DB E&C collaborates with Israeli engineers to address technical and safety challenges and ensure the program's outcome.

Tel Aviv Red Line, Israel

DB Engineering & Consulting (DB E&C) worked on the Tel Aviv Red Line project, focusing on system integration, interface and requirements management, system assurance, testing, and acceptance. This light rail transit system is the first of four lines in the Tel Aviv-Yafo metropolitan area, extending from Bat Yam in the south to Petah Tikva in the northeast, with a significant underground portion. DB E&C served as the internal and external system integrator for the entire Red Line project, collaborating with various stakeholders.[26][27]  

Doha Metro, Qatar

DB E&C worked on the development and construction of the Doha Metro in Qatar. It provided technical and project management expertise for the design, tender process, and final implementation of the metro system, including its various phases and operational lines. Additionally, DB E&C supported the establishment of a Railway Safety Regulatory Body to ensure the safe operation of the Doha Metro network and other railway operators in Qatar.[28][29][30]

Al Mashaaer Al Mugadassah Metro, Mecca, Saudi Arabia

DB Engineering & Consulting provided construction, operation, and maintenance supervision for a rail-based mass transit system in Mecca, Saudi Arabia, aimed at improving transportation for millions of pilgrims during the annual Hajj. Constructed by China Railway Construction Corporation (CRCC) in 21 months, the system connects holy sites like Jamarat, Mina, Muzdalifah, and Arafat. Phase 1 commenced in November 2010, followed by Phase 2 a year later, with a capacity for approximately 400,000 pilgrims.[31]

Australia

Sydney Metro

DB E&C provides a large part of the planning services in the areas of equipment technology, vehicles, acceptance/commissioning, and operation for the construction and launch of the first fully automated metro in Sydney. The first section between Rouse Hill and Chatswood (Sydney Metro Northwest) went into operation at the end of May 2019. A second section to Bankstown is also scheduled to go into operation in 2024.[32]

Asia

Eastern Dedicated Rail Freight Corridor, India

DB Engineering and Consulting GmbH (DB E&C) has been commissioned as the project management consultant (PMC) for the construction of a single-track electrified heavy haul railway track for the Pilkhani - Sahnewal section of the Eastern Dedicated Freight Corridor. This section is part of the larger initiative by the Dedicated Freight Corridor Corporation of India Limited (DFCCIL) to establish dedicated freight corridors across India. The PMC's responsibilities include monitoring contractor progress, liaising with DFCCIL staff, and ensuring safety compliance during construction near busy railroad tracks and public utilities.[33][34][35]

Germany

Stuttgart-Ulm rail project

DB E&C and its responsible project company are involved in the Stuttgart 21 project and the new Wendlingen-Ulm line, where they are working on behalf of DB Netz AG (now DB InfraGO). Among other things, DB E&C is responsible for geodetic services, overall planning and planning approval for the dismantling of the old Stuttgart Central Station, and construction supervision of the entire project. The company is also responsible for the planning and contract award supervision of the Stuttgart Digital Node, which is based on Stuttgart 21.[36]

Gateway Gardens district, Frankfurt am Main

The new S-Bahn connection includes both the construction of the new Gateway Gardens station and the laying of the S-Bahn tracks between Frankfurt-Stadion and the Frankfurt Airport regional train station. Route 3683 (Flughafenschleife), between Frankfurt-Stadion and Frankfurt Airport, was relocated to the East. For this purpose, a four-kilometer-long new double-track section was constructed. 50 per cent of this line is underground and was built using an open construction method. The new track construction was divided into 16 construction stages. The decommissioning and recultivation of the old existing line between the eastern portal of the existing airport tunnel and the stadium connection was also part of the project. In addition, safety standards in the existing airport tunnel were adopted. The line was put into commercial operation on December 15, 2019.

For this project, DB Engineering & Consulting was commissioned to provide design services to connect the DB line running between Frankfurt (Main) Stadion station and Frankfurt (Main) Flughafen regional station to an underground suburban train station in Gateway Gardens, as well as to provide construction management services.[37]

Hanover Central Station, Lower Saxony

DB E&C is involved in the conversion and extension of Hanover Central Station to meet urban development requirements and increased traffic volume. It is also one of the first major Building Information Modeling (BIM) projects for DB. The project encompasses renewing 59 civil engineering structures affecting six platforms, including platforms, roofs, drainage, conveyor technology, technical equipment, and structural engineering elements. Additionally, access to the bridge is provided as part of the maintenance concept.[38][39]

ICE depot in Cologne-Nippes

DB Engineering & Consulting (DB E&C) oversaw the construction of the ICE depot in Cologne-Nippes, which commenced operation in June 2018. The depot services all ICE series from ICE 1 to ICE 4, with a workshop featuring four 410-meter-long tracks capable of accommodating double-traction trains. Additionally, ancillary facilities such as exterior cleaning and de-icing, underfloor lathe, and interior cleaning facilities were included. Throughout construction, operational continuity of adjacent tracks was maintained, necessitating track relocation and the dismantling of existing structures.[40]

Karlsruhe-Basel

DB Engineering & Consulting contributed planning, construction supervision, realisation management, and consulting services to the Expansion/New-Built Line Karlsruhe-Basel project. National and international rail traffic between Rotterdam and Genoa relies on this line, which underwent upgrades to increase capacity and shorten travel times. Divided into nine sections covering 182 km, the project aimed to segregate traffic and boost speeds to 250 km/h. DB E&C's activities encompassed planning, construction supervision, implementation management, environmental investigations, and support for inspection and acceptance procedures.[41]

Upper Elbe valley, Saxony

DB E&C provided project control and planning services for the multilayered construction site in Upper Elbe valley, Saxony. This project aimed to modernize the heavily used line between Dresden and Schöna/international border (D/CZ) to ensure its future availability. DB E&C's services included technical and commercial project management, design, and ecological construction supervision. Works involved renewing the permanent way, replacing culverts and railroad overpasses, and upgrading switches at various stations along the line. These projects were implemented between 2016 and 2020, with further developments in 2022.

Riedbahn Corridor Project

DB Engineering & Consulting is involved in Deutsche Bahn's modernization efforts for the German rail network. DB E&C focused on design, construction supervision, environmental services, and validation and assessment. For example, DB E&C conducts drone flights and 360° video recordings to facilitate detailed area surveys and construction supervision. One significant project includes the extensive modernisation of the Riedbahn, a 70-kilometre line between Frankfurt am Main and Mannheim, which aims to enhance infrastructure and increase flexibility in rail transport.[42]

References

  1. ^ Pleister, Christopher (2012-03-23). "The Federal Agency for Financial Market Stabilisation in Germany: From Rescuing to Restructuring". OECD Journal: Financial Market Trends. 2011 (2): 155–165. doi:10.1787/fmt-2011-5k9cswmzxcbp.
  2. ^ "Projects in the Pan-European Corridor IV". Global Railway Review. Retrieved 2024-06-04.
  3. ^ Menius, Reinhard; Matthews, Volker (2017-03-28). Bahnbau und Bahninfrastruktur: Ein Leitfaden zu bahnbezogenen Infrastrukturthemen (in German). Springer-Verlag. ISBN 978-3-658-17177-3.
  4. ^ International2016-04-04T10:09:00+01:00, Railway Gazette. "Merger forms DB Engineering & Consulting". Railway Gazette International. Retrieved 2024-06-04.{{cite web}}: CS1 maint: numeric names: authors list (link)
  5. ^ "Handelsblatt". www.handelsblatt.com. Retrieved 2024-06-04.
  6. ^ Redaktion (2016-07-06). "Integration des DB Umweltservice in die DB Engineering & Consulting GmbH". Privatbahn Magazin (in German). Retrieved 2024-06-04.
  7. ^ Zeitung, Märkische Allgemeine (2024-06-04). "Die Deutsche Bahn produziert in ihrem Umweltlabor in Kirchmöser selbst Desinfektionsmittel". www.maz-online.de (in German). Retrieved 2024-06-04.
  8. ^ "SAR cooperates with DB Rail Academy for workforce skills development". Global Railway Review. Retrieved 2024-06-04.
  9. ^ Scholz, Heiko; Academy, Global Director DB Rail; Consulting, Head of Competence; Engineering, D. B.; Consulting 2022-11-16T05:00:00. "Future Skills: Gaining expertise from step-by-step training". Railway Gazette International. Retrieved 2024-06-04.{{cite web}}: CS1 maint: numeric names: authors list (link)
  10. ^ Iris, Hausladen (2022-04-01). "Remote Consulting in der Logistikberatung – Ein Erfolgsmodell?". Der Betriebswirt. 63 (2): 97–106. doi:10.3790/dbw.63.2.97. ISSN 2628-7846.
  11. ^ "Deutsche Bahn Experts To Help Modernize Odesa Port's Railway Infrastructure". en.cfts.org.ua. 2024-06-03. Retrieved 2024-06-04.
  12. ^ "Ukrzaliznytsia And Deutsche Bahn To Cooperate On Energy Management". en.cfts.org.ua. 2024-06-03. Retrieved 2024-06-04.
  13. ^ "Ukrainian Grain Hoppers Can Reach 4 European Ports - DB Engineering & Consulting". en.cfts.org.ua. 2024-06-03. Retrieved 2024-06-04.
  14. ^ "California High-Speed Train Staff Recommends German Rail Operator - CBS San Francisco". www.cbsnews.com. 2017-10-06. Retrieved 2024-06-04.
  15. ^ "DB ENGINEERING & CONSULTING overview - Find and update company information - GOV.UK". find-and-update.company-information.service.gov.uk. Retrieved 2024-06-04.
  16. ^ "DB Engineering & Consulting GmbH". www.bloomberg.com. Retrieved 2024-06-04.
  17. ^ "Продолжение сотрудничества ҚТЖ с немецкой DB Engineering & Consulting". zdmira.com (in Russian). 2023-10-17. Retrieved 2024-06-04.
  18. ^ dpa (2022-07-25). "Milliardenprojekt: Deutsche Bahn an Bahnausbau in Ghana beteiligt". Die Zeit (in German). ISSN 0044-2070. Retrieved 2024-06-04.
  19. ^ "Projektmanagement in 80634 München | DB Engineering & Consulting". www.schienenverkehrsportal.de. Retrieved 2024-06-04.
  20. ^ Salian, Neesha (2022-09-27). "Etihad Rail concludes knowledge transfer programme with Deutsche Bahn". Retrieved 2024-06-04.
  21. ^ "Многофункциональность и партнерство: Проекты Deutsche Bahn на внешних рынках". cfts.org.ua (in Russian). Retrieved 2024-06-04.
  22. ^ "Al-Haramain: Pilgerfahrt mit 300 km/h: Hochgeschwindigkeitszug nach Mekka". www.kleinezeitung.at (in German). 2018-10-12. Retrieved 2024-06-04.
  23. ^ "Saudi-Arabien nimmt Highspeed-Zug durch die Wüste in Betrieb". Der Spiegel (in German). 2018-10-11. ISSN 2195-1349. Retrieved 2024-06-04.
  24. ^ NACHRICHTEN, n-tv. ""Al-Haramain" nimmt Betrieb auf". n-tv.de (in German). Retrieved 2024-06-04.
  25. ^ "Bahn baut Schienennetze im Nahen Osten - WELT". DIE WELT (in German). 2015-09-22. Retrieved 2024-06-04.
  26. ^ זגריזק, אסף (2023-03-01). "פרויקט המטרו בישראל: 7 קבוצות הגישו הצעות למכרז". Globes. Retrieved 2024-06-04.
  27. ^ "רק שלוש יזכו: שבע קבוצות ניגשו למכרז לניהול קווי המטרו | כלכליסט". calcalist (in Hebrew). 2023-03-01. Retrieved 2024-06-04.
  28. ^ "Projects – Arab Urban Development Institute". Retrieved 2024-06-04.
  29. ^ "Doha Metro". Railway Technology. Retrieved 2024-06-04.
  30. ^ "Fußball-WM 2022: Bahn-Fahren in Qatar". FAZ.NET (in German). 2022-12-02. Retrieved 2024-06-04.
  31. ^ IMF. Middle East and Central Asia Dept. (2012). "Regional Economic Outlook, November 2012: Middle East and Central Asia: Middle East and Central Asia". Regional Economic Outlook. doi:10.5089/9781475510812.086. ISBN 978-1-47551-081-2. ISSN 2071-4165.
  32. ^ Dharma, RanjithKumar (2022-12-22). "Siemens Mobility secures Sydney Metro contract". Railway Technology. Retrieved 2024-06-04.
  33. ^ "Five engineering groups selected to bid for Hyderabad airport metro". The Times of India. 2022-12-29. ISSN 0971-8257. Retrieved 2024-06-04.
  34. ^ Bureau, The Hindu (2022-12-21). "Five consortia in race for General Consultant role in Airport Metro". The Hindu. ISSN 0971-751X. Retrieved 2024-06-04.
  35. ^ "Handelsblatt". www.handelsblatt.com. Retrieved 2024-06-04.
  36. ^ "Stuttgart 21 Project, Germany". Railway Technology. Retrieved 2024-06-04.
  37. ^ Mollenhauer, Michael; Sommerlatte, Tom (2016), "Transformationale Führung – vorleben und Inspirieren: Deutsche Bahn", Vertrauensbasierte Führung, Berlin, Heidelberg: Springer Berlin Heidelberg, pp. 93–97, doi:10.1007/978-3-662-46233-1_15, ISBN 978-3-662-46232-4, retrieved 2024-06-04
  38. ^ "Central station Hanover". ZPP Ingenieure AG. Retrieved 2024-06-04.
  39. ^ Schenck, Douglas; Wilson, Peter (2017), BIM building information modeling, vol. Ernst and Sohn Special, Oxford University Press, doi:10.1093/oso/9780195087147.003.0012, ISBN 978-0-19-508714-7, retrieved 2024-06-04
  40. ^ Communications, U. I. C. (2024-06-04). "Germany: DB Engineering & Consulting begins operations as of April". UIC Communications. Retrieved 2024-06-04.
  41. ^ "Karlsruhe-Basel Railway Line Upgrade, Germany". Railway Technology. Retrieved 2024-06-04.
  42. ^ Crumley, Bruce. "Deutsche Bahn Using Drones for its Massive Riedbahn Railway Construction Project". enterprise-insights.dji.com. Retrieved 2024-06-04.
This page was last edited on 5 June 2024, at 09:59
Basis of this page is in Wikipedia. Text is available under the CC BY-SA 3.0 Unported License. Non-text media are available under their specified licenses. Wikipedia® is a registered trademark of the Wikimedia Foundation, Inc. WIKI 2 is an independent company and has no affiliation with Wikimedia Foundation.